前河金矿充填体稳定性分析及其应用 被引量:1

STABILITY ANALYSIS OF FILL-MASS AND ITS APPLICATION IN QIANHE GOLD MINE
在线阅读 下载PDF
导出
摘要 前河金矿矿体属矿岩破碎的难采倾斜薄矿脉,设计采用下向分层充填法开采,而充填体设计强度直接影响到该采矿法的成败。文中针对前河金矿的具体条件,认为充填失稳破坏的两种可能形式是倾倒失稳和弯曲受拉破坏,并分别进行了分析计算。在此基础上,采用了多种新技术、新工艺,而且取得了较好的应用效果。 The orebody of Qianhe Gold Mine belongs to dip and narrow vains with ore-rock fractured and difficult to mine, which is planned to mine with underhand cut-and-fill stoping but the designed strength of fill-mass exerts influence directly on the success or failure of the mining method. This paper, in the light of the actual conditions of Qianhe Gold Mine, considered that two possible forms of fill instability or failure would be tip-over instability and bent-and-tensioned failure and performed analysis and calculation to them respectiyely. Based on the results of above analysis and calculation, several new techniques and new process were adopted and good results were obtained.
作者 廖世金
机构地区 长沙矿山研究院
出处 《矿业研究与开发》 CAS 1997年第3期40-43,共4页 Mining Research and Development
关键词 充填体 强度 稳定性 承载层 金矿 采矿 Fill-mass strength, Stability, Load-bearing layer, Cement content, Loessal clay
  • 相关文献

参考文献1

  • 1周先明.下向胶结充填采场充填体作用机理研究的理论与实践[J]黄金,1988(05).

同被引文献6

引证文献1

二级引证文献4

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部