摘要
A precedence order is defined based on the release dates of jobs' direct successors. Using the defined precedence order and Heap Sort, a new polynomial algorithm is provided which aims to solve the parallel scheduling problem P|pj = 1, r j, outtree| ∑Cj Cj. The new algorithm is shown to be more compact and easier to implement.
A precedence order is defined based on the release dates of jobs' direct successors. Using the defined precedence order and Heap Sort, a new polynomial algorithm is provided which aims to solve the parallel scheduling problem P|pj = 1, r j, outtree| ∑Cj Cj. The new algorithm is shown to be more compact and easier to implement.
基金
This work was supported by the National Natural Science Foundation of China(No.60474023)
Science and Technology Key Project Fund of theMinistry of Education(No.03184)
the Major State Basic Research Development Program of China(No.2002CB312200).