摘要
对某超大基坑前期施工中产生的各种变形及变形量进行了细致深入的分析,对后续阶段的基坑施工提出了一些合理化建议,且对部分变形量做出了大胆的预测。相对于在基坑完全施工结束后做出的基坑监测分析报告来说,阶段性变形分析及预测才是真正意义上的信息化施工,同时更真正达到了监测的技术经济效果。
In this paper, various kinds of distortion and deformation amount in the previous construction of super-sized foundation pit are analyzed carefully and deeply, and then some reasonable suggestions on the construction of the foundation pit in the following stages, are proposed while some deformation amounts are forecasted. Compared with the supervision and analysis report on the foundation pit after completion of its construction, the phased deformation analysis and forecast are the real information-based construction, and, meanwhile, can obtain actual effect of technology and economy of supervision.
出处
《建筑科学》
北大核心
2007年第11期89-93,85,共6页
Building Science
关键词
监测
变形分析
预测
施工指导
supervision
analysis of distortion
forecast
construction direction