海底天然气管道投产案例分析 被引量:10

A CASE STUDY ON THE COMMISSIONING OF SUBSEA NATURAL GAS PIPELINE
在线阅读 下载PDF
导出
摘要 为防止形成天然气水合物,天然气管道在投产前必须彻底干燥。海底管道距离长,不能分段施工,多采用清管器组加干燥剂的作业方案,这就存在清管器组的运行控制、卡球和窜漏等问题,作业难度高、风险大。针对我国海底输气管道投产前干燥施工过程中出现的憋压、卡球、窜漏和清管器磨损等问题进行了分析,说明了发生问题的原因。对比研究了不同管道干燥方案的优缺点、清管器使用的合理性、干燥剂使用效果和干燥指标的制定与监测方法等问题。在此基础上,提出了针对海底天然气管道的凝胶、干燥剂和多盘清管器的组合干燥方案。该方案能有效解决密封、卡球和凝胶滞留等问题,并能确保施工质量,对类似工程有借鉴意义。 The natural gas pipeline needed to be desiccated thoroughly before going on stream.The subsea pipeline is long and can not be constructed sectionally,so the operation proposal of the combination of the cleaning pig and dryers are often a-dopted.Therefore,that will incur some problems in operation control,pig jam and leakage,etc.,and the operation is of great difficulties and risks.This paper analyzed a variety of problems during the drying and construction before the subsea gas transmission pipeline was put into operation,like the pressure suppression,pig jam.leakage and the pig attrition wear,etc.It also spelled out the reasons for these problems.It studied the disadvantages and advantages of various kinds of pipe dryers,the ra-tionality of pig application,the performance of dryers,the establishment of the dryers index as well as the monitor methods,etc.The paper brought forth a drying proposal which combines gel,dryer and cleaning pig.This proposal can effectively solve the said problems in airproof,pig jam and the residence of gel,etc.whereby to guarantee the construction quality.It can provide references to the similar projects.
作者 于达
出处 《天然气工业》 EI CAS CSCD 北大核心 2007年第10期109-111,共3页 Natural Gas Industry
关键词 水下管道 输气管道 干燥 投产 方案 对比 underwater pipeline,gas transmission pipeline,drying,commissioning,proposal,comparison
  • 相关文献

参考文献3

二级参考文献6

  • 1[1]Christian Falck. Pecommissioning and commissioning Europipe: an environment challenge. Pipe Line & Gas Industry and & Pipeline International,May 1996
  • 2Maribu Jarleiv,Falck Christan,Clenshaw Richard.The Zeepipe Experience:Pigging 814km of subsea gas pipeline in the North Sea.Pipes and Pipelines International,1994:16-22
  • 3Gunnar Kopp Jr.Why and how to dry gas pipe lines.Pipe Line Industry,October 1981:35-41
  • 4Falck Christian,Maribu Jarleiv,Engeland Gordon.Precommissioning and commissioning Europipe- an environment challenge.Pipes & Pipeline Industry,July-August 1996:16-22
  • 5Kalli C J,Cowie D.Hydrates:towards the complete solution.SPE 20958,1990
  • 6Falck Christian ,Maribu Jarleiv ,Eide L O.Commissioning The zeepipe system sets new standards.Pipeline &Gas Journal,August 1994:24- 33

共引文献25

同被引文献68

引证文献10

二级引证文献47

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部