摘要
文章以西柏坡电厂三期扩建工程为例,介绍了采用护坡桩结合锚杆(辅以网喷混凝土技术,在具有动力荷载的铁路边缘对深基坑进行支护)的设计和施工方法。
Using Xibaipo Power Plant Phase 3 expansion project as an example, this paper introduces the design and construction methods of combined pile revetment and rock bolt (supplemented by gunite technology, supporting deep foundation pits near the edge of railway under dynamic loads).
出处
《电力建设》
2007年第10期80-82,共3页
Electric Power Construction
关键词
深基坑
支护方案
设计
施工
deep foundation pit
supporting scheme
design
construction