摘要
从三峡电站水头的运行特性出发,分析水轮机在高水头及低水头运行时的稳定性问题,并提出改善高水头运行稳定性的综合治理措施。
According to the head operating characteristics of Three Gorges project, the operating stability of hydraulic turbines under high and low head is analyzed, meanwhile,comprehensive measures for improving stability at operating zone for high head are presented.
出处
《东方电气评论》
1997年第2期84-90,122,共8页
Dongfang Electric Review
关键词
三峡电站
水轮机
运行
压力脉动
Three Gorges Project,Hydraulic turbine,Operation,Pressure Pulsation.