摘要
设计了考虑电力系统安全的输电网规划流程,改变了传统规划只考虑N安全和N-1安全的规划模式,进一步计算分析了规划网络在N-2安全情况下的缺电成本。文中采用故障筛选再规划的方式提高了N-1安全规划的计算速度,实现了大规模规划问题的求解,满足工程应用需要。18节点系统及实际电网147节点系统的计算结果表明,该方法行之有效。
The process of transmission network planning considering the electric power system security is designed in this paper. It has renovated the traditional planning method in which only N secure rule and N-1 secure rule are considered, and the load shedding costs of the planning network in N-2 condition are further analyzed. The fault selection step is first carried out so that the computing of the N-1 security network planning can be speeded up and the large real network planning can be realized meeting the demand of engineering applications. Tests on the 18-bus system and a real power network of 147-bus system show that the method proposed is effective.
出处
《电力系统自动化》
EI
CSCD
北大核心
2007年第11期35-38,73,共5页
Automation of Electric Power Systems
基金
上海市重点科技攻关项目(041612012)
高等学校优秀青年教师教学科研奖励计划资助项目~~
关键词
电力系统安全
输电网规划
启发式方法
N-1安全网络
N-2安全校验
缺电成本
electric power system security
transmission network planning
heuristic algorithm
N-1 secure network
N-2secure test
load shedding cost