结合龙溪隧道工程概况及围岩情况,确定了隧道开挖及揭煤方案,从瓦斯释放、通风、瓦斯监控三方面介绍了高瓦斯情况下,隧道施工采取的防瓦斯突出措施,并提出了施工注意事项,以有效防止瓦斯事故的发生。
Combined with engineering situations and surrounding rock conditions of Longxi tunnel excavation scheme is determined. From three aspects: gas drainage, ventilation and gas monitoring measures to prevent gas outburst are proposed for tunnel construction. Matters deserving attention are pointed out to prevent gas accident.
出处
《山西建筑》
2007年第4期310-311,共2页
Shanxi Architecture
关键词
高瓦斯
隧道开挖
通风方式
监控系统
high gas, tunnel excavation, ventilation way, monitoring system