掌鸠河引水工程穿越断裂带工程措施 被引量:4

Engineering Measures for Faulted Zones of the Zhangjiuhe Water Transfer Project
在线阅读 下载PDF
导出
摘要 掌鸠河引水供水工程厂口隧洞位于输水线路后段,隧洞斜穿普渡河断裂带,岩体破碎、质软,隧洞围岩稳定性很差,为此,采用了特殊的、有针对性的结构措施和施工方法。过普渡河断裂带洞段在实施超前地质预报、超强一次支护、及时跟进二次衬砌、短循环进尺等具体工程措施保障下顺利贯通。 The intake tunnel of the Zhangjiuhe Water Transfer project, located at the lower section of the water transfer alignment, runs diagonally through the Puduhe faulted zone where the rocks are weak and highly fractured resulting in poor stability. So some special and unusual engineering methods and structures were adopted accordingly. The tunnel section at the Puduhe fault zone was successfully completed with the application of engineering measures including the forecasting of geological conditions, super-intensive primary support, timely secondary lining and close-cycle advance.
出处 《水力发电》 北大核心 2006年第11期69-70,共2页 Water Power
基金 云南省院省校科技合作项目(00YT02)
关键词 引水隧洞 断裂带 支护措施 灌浆 超前预报 泥石流 掌鸠河引水工程 diversion tunnel faulted zones support grouting forecast debris flow Zhangjiuhe Water Transfer Project
  • 相关文献

同被引文献24

引证文献4

二级引证文献5

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部