西龙池抽水蓄能电站高压岔管考虑围岩分担内水压力设计现场结构模型试验研究 被引量:2

Experimental study on site structural model for design of surrounding rock to share internal water pressure for high pressure Y-pipe of Xilongchi pumped-storage power station
在线阅读 下载PDF
导出
摘要 西龙抽水蓄能电站岔管规模远超过国内已建工程,为降低制作、安装难度,考虑岔管与围岩联合受力设计。在大量结构分析基础上,通过现场结构模型试验对埋藏式岔管实际受力状态和施工工艺的模拟,为设计参数取值、岔管与围岩联合受力规律研究,提供重要的科学依据。 In view of very large scale of Y-pipes of this project, the design of combined bearing of Y-pipe and surrounding rock is adopted to decrease the difficulty of fabrication and erection. This test provides the important bases for determining the design parameters and studying the combined bearing law of the Y-pipe and surrounding rock modeling under actual bearing conditions and the construction technology of Y-pipe tests of site structural model.
出处 《水力发电学报》 EI CSCD 北大核心 2006年第6期55-60,54,共7页 Journal of Hydroelectric Engineering
关键词 水工结构 围岩分担内水压力 现场模型试验 内加强月牙肋岔管 抽蓄能电站 西龙池 hydraulic structure surrounding rock to share internal water pressure site model test crescent ribbedY-pipe pumped-storage power station Xilongehi
  • 相关文献

参考文献3

  • 1王志国.内加强月牙肋岔管技术研究专题研究报告[R].国家电力2001年科技项目.北京:北京勘测设计研究院,2004年12月.
  • 2段云岭,张义.西龙池抽水蓄能电站钢岔管现场结构模型试验报告[R].北京:清华大学土木水利工程学院,2005年1月.
  • 3钟秉章,陆强.西龙池抽水蓄能电站内加强月牙肋岔管三维有限元分析研究报告[R].杭州:浙江大学固体力学研究所,2003年10月.

共引文献1

同被引文献15

引证文献2

二级引证文献13

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部