摘要
本文对葛洲坝至上海直流输电系统单极系统调试期间进行的典型的无功功率控制试验结果进行分析并对控制性能作出评价。
This paper gives the analysis for the typical reactive power control test during the commissioning of the pole 1 of Geshang HVDC project. Acoording to the results, the control performance is also descussed.
出处
《电网技术》
EI
CSCD
北大核心
1990年第4期29-33,共5页
Power System Technology