摘要
汕头海湾悬索桥主缆采用PWS法设计和架设。其导索、猫道、主缆钢丝束拉就位,垂度调整,挤紧成圆。
Main cables of Shantou Bay Suspension Bridge are designed and erected in accordance with PWS (i.e. prefabricated parallel wire strand) method, and key points to design and erection of the cables, such as pilot rope, catwalk, and towing, sag adjusting, compacting of wire strands are hereby elaborated.
出处
《桥梁建设》
EI
CSCD
北大核心
1996年第4期42-47,共6页
Bridge Construction
关键词
主缆钢丝束
架设
汕头海湾大桥
悬索桥
pilot rope, catwalk, towing system, erection of wire strand of main cable