摘要
某新建氧化铝厂水源为乌江在建构皮滩电站库区,取水点处于乌江中游峡谷段,水位变幅43.33 m,取水各项条件相对复杂,工程设计和实施难度较大。本文分析了各拟选取水方案的可能性和存在的问题,最终提出浮船和岸边式泵站组合取水方案,较彻底地解决了所面临的工程难题。
A new alumina refinery is scheduled to source the water from Goupitan Reservoir (hydraulic power generation station) on Wujiang River with the water - taking point at gorge section of middle stream and with the water - level variation 43.33 meters. It involves pretty complicated conditions for water taking and rather difficulty for project engineering and implementation. Possibility of each scheduled water - taking option and the problem existed were analyzed, a combined option of floating- boat + river- bank pump station was proposed to thoroughly solve the problem faced by the project.
出处
《贵州工业大学学报(自然科学版)》
CAS
2006年第5期25-27,共3页
Journal of Guizhou University of Technology(Natural Science Edition)
关键词
氧化铝厂
乌江
构皮滩水库
取水
水位
组合
alumina refinery
wujiang river
goupitan reservoir
water taking
water level
combination