市第六人民医院特需病房大楼基坑周边情况较复杂,围护桩的选型是关键。应用安全性、经济性、工期、施工方便性这四要素,对地下连续墙、钻孔灌注桩、SMW工法等围护桩进行定量分析,最后选定采用SMW工法为本工程的围护桩,并取得成功。
Owing to quite complex circumstance of foundation pit for Special Ward Building of Shanghai aphragm No. 6 People Hospital, it is key to select type of enclosure of pile. Quantitive analysis of diaphragm wall, bored cast-in-place pile, SMW method etc was carried out with four key factors such as security, economy, construction period and convenience. Finally, SMW method was selected as enclosure of pile for this project and success achieved.
出处
《上海建设科技》
2006年第5期47-48,61,共3页
Shanghai Construction Science & Technology
关键词
基坑
围护桩
安全性
经济性
工期
施工方便性
foundation pit enclosure of pile security economy construction periodconstruction convenience