摘要 岳阳电厂旧输灰系统原设计为带低压气力连续泵的外旁通管和水力除灰联合的飞灰处理系统,运行多年来系统存在诸多问题,采用双套管紊流输灰技术进行了改造。分析了设计改造调试过程中存在的设备选型、系统设计优化问题并提出了改进方法。根据双套管系统特点对其原理、操作参数调整变化进行了说明。此系统为紊流浓相输送,其输灰管独特结构基本避免了输灰过程中的输灰管堵塞。实践证明该系统运行效果良好,经济性安全性上有明显提高。 The previous ash conveying system in Yueyang Power Plant was a fly-ash handling system designed to be the combination of outerbypass pipe with low-pressure pneumatic continuous pump and hydraulic system. There are many problems during the operation for years. The turbulent double-pipe ash conveying technology was used to retrofit the system and several relative problems were introduced, such as equipment selection, system design and optimization etc. Based on the features of this double-pipe system, the working principle and variation of operation parameters were discussed. This system is turbulent dense-phase conveying, and the specially designed delivery ash pipe can prevent the blockage during ash conveying. The application results show that this system is of better operation effects, in addition, the economy and safety have been improved effectively.
作者 丁岩峰
出处 《中国电力》 CSCD 北大核心 2006年第10期69-72,共4页 Electric Power
关键词 紊流双套管 密相 气力输灰系统 turbulent dual-tube dense state pneumatic ash conveying system
  • 相关文献

参考文献1

二级参考文献4

  • 11,Heat Exchanger Design Handbook, Vol.2, Fluid Mechanics and Heat Transfer, Emst U. Schlunder, Editor-in-Chief, Hemisphere Publishing Corporation, 1983.
  • 23,Soo S L. Fluid Dgnamics of Multiphase Systems, Blaisdell, Waltham, Mass, 1967.
  • 34,Zenz F A, and Othmer D F. Fluidization and Fluid-Particle Systems. New York: Reinhoid, 1960.
  • 42000-06-28

共引文献5

同被引文献21

引证文献3

二级引证文献7

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部