摘要
文中从管片预制厂生产规模的确定、管片厂生产方法的选定、管片预制厂功能设计、各功能区的具体设计(钢筋生产区,管片生产区,管片静养区、附属设施、各功能区的高度确定)、各功能区的平面布置、预制管厂建设六方面阐述了预制混凝土管片厂设计的要点。
This paper presents the brief introduction of the main design points of the factory to precast tunnel concrete lining segment from 6 aspects. They are: (1) determining the production scale of factory, (2) selecting the production method, (3) function design of the factory, (4)concrete design of every production function area, (5) the plan layout of every production function area, (6) the construction of factory.
出处
《山西水利科技》
2006年第4期37-38,40,共3页
Shanxi Hydrotechnics
关键词
TBM
预制混凝土管片
管片模具
蒸汽养护
静养
TBM precast tunnel concrete segment precast form of tunnel concrete segment autoclaving stationary curing