摘要
在深入研究的基础上,本文主要对注浆胶结矿柱充填工艺与人工挖边槽胶结充填工艺在上向水平采矿法矿山中的实践应用作了系统的分析与研究,通过对充填质量、充填效率、充填劳动强度等方面的比较论证,得出了注浆胶结矿柱充填工艺具有施工方便、充填效率高、充填质量好、采场回采周期短、贫损两率指标低等一系列优点,从而确定了注浆胶结矿柱充填工艺对上向水平采矿法的矿山而言,是一种优势明显、切实可行的充填工艺。
Based on the penetrate into study, the paper systematically analyzed and summarized the application on the cemented stowing of digging groove and clot of injection in the horizontal sub - level mining. According to compare proof by sufficiency ,operating efficiency , intention of labor of cemented stowing ,we draw the conclusion that cement stowing of separate wall have a series of advantage, such as facility, high efficiency , good quality ,decrease every sub-level mining period and poverty rate etc. There by it is verified that cemented stowing of separate wall is efficacious in the mine that mining method is horizontal sub -level mining.
出处
《黄金科学技术》
2006年第3期23-25,共3页
Gold Science and Technology
关键词
注浆
边槽
胶结体
水平分层
clot of injection
groove on the side
cemented stowing
horizontal sub - level