摘要
苏通大桥主桥6、7、8号墩的特大型钢吊箱采用整体吊装施工工艺。基于施工实践,重点介绍吊箱整体吊装的关键技术。
The techniques of integral hoisting of the super steel cofferdam is adopted in No. 6, No. 7 and No. 8 main piers of the Sutong Bridge. On the basis of the construction practices, the key techniques of the integral hoisting of cofferdams are introduced mainly.
出处
《公路》
北大核心
2006年第8期84-90,共7页
Highway
关键词
苏通大桥
钢吊箱
整体吊装
关键技术
Sutong Bridge
steel cofferdam
integral hoisting
key techniques.