长江三峡永久船闸一期开挖爆破实践 被引量:1

EXCAVATION AND BLASTING PRACTICE IN THE FIRST PHASE OF PERMANENI SHIP LOCK IN THE THREE GORGES PROJECT
在线阅读 下载PDF
导出
摘要 三峡水利枢纽永久船闸一期开挖工程量达1800万m3,合同工期为18个月,平均月强度达100万m3;岩性为古老的前震旦纪闪云斜长花岗岩,构造裂隙发育,地质条件较复杂;设计开挖深度为90m,对安全稳定要求高,施工强度相当大。在工程实践中采用全套大型液压机械设备,混装车乳化浆状炸药塑料导爆管雷管大区接力微差起爆及光面爆破、预裂爆破等施工技术,取得了较好的效果,提前8天完成一期开挖任务。 In the first phase, the total volume of rock excavation of permanent shiplock in the Three Gorges Project amounts to 18 million m3,1 million m3 in average for each month. The contracted construction duration is 18 months. The rock is amphibole-micaplagioclase-granite in pre-sinian period.Structural cracks in rock mass is grown seriously,and the rock geological condition is complex, while the desired slope stability is strict. In the rock excavation,huge hydraulic mechanical equipments,explosive mixed trucks, methods of smooth blasting, presplit blasting and delay blasting which are fired in series within a large area,a better effect is obtained, and the excavation time has been shorted for 8 days.
出处 《工程爆破》 1996年第4期6-11,共6页 Engineering Blasting
关键词 岩体 开挖 光面爆破 预裂爆破 船闸 爆破 The Three Gorges Project Excavation of rock mass Smooth blasting Presplitting blasting
  • 相关文献

引证文献1

二级引证文献5

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部