摘要
针对留驾水电站YT-3500型调速器运行中出现的问题,进行了调速系统的改造设计,选用先进的WBZT-50型步进式调速器代替原调速器,对系统的电气及机械部分进行了重新配置,介绍了改造后调速系统的设备配置、主要技术参数以及运行方式,解决了原系统存在问题,运行效果十分良好。对水电站调速器的改造及运行具有现实的指导意义。
A reformation design is conducted for the governing system to solve the problem in the operation of type YT—3500 speed governing in Liujia water power station.The advanced step-by-step speed governing of type WBZT—50 is chosen to replace the original one.Consequently the problem in original system is thoroughly solved and the operation is in good condition.A detailed introduction is given in this paper about the equipment disposition,main technical parameters and operation of the reform governing system.This has instructive meaning for the reformation and operation of old governing system in water power stations.
出处
《西华大学学报(自然科学版)》
CAS
2006年第4期98-100,共3页
Journal of Xihua University:Natural Science Edition
关键词
水电站
调速系统
改造
运行
water power station
speed governing
reform
operation