以北京地铁4、10号线黄庄站工程实例,通过对施工过程中监控量测结果的分析,总结在浅埋暗挖法施工过程中地表沉降产生的原因及沉降规律。对影响地表沉降的各种因素进行分析,针对施工对周边环境的影响,提出控制地表沉降的措施,对4号线后续工程施工以及10号线黄庄站施工起到指导作用。
Through the analysis of the monitoring results in the construction of Huang Zhuang Stations of Beijing Metro Line No.4 and Line No.10,the mechanism of ground settlement during mining of shallow station is induced.Analysis on the factors influencing the ground settlement is made.With regard to the construction(effect) on surrounding areas,the control measures for ground settlement are proposed, which will be a guide for the construction of the following stations in Line No.4 and in Line No.10.
出处
《地下工程与隧道》
2006年第1期27-30,38,共5页
Underground Engineering and Tunnels