摘要
以莱钢万力H型钢有限公司抽柱换梁工程为例,介绍行车梁拼装、柱加固拆除及托粱吊装前后的测量观测。
Taking the pillar erection and beam reconstruction project of Laigang Wanli H - section Co. , Ltd. as an example,the paper introduces the crane beam assembly, pillar reinforcement and deconstruction and the survey and observation before and after the lift and assembly of supporting beam.
出处
《莱钢科技》
2006年第1期24-27,共4页
Laigang Science & Technology
关键词
抽柱
工业厂房
焊接
pillar withdrawing, industrial workshop, welding