摘要
较全面的列出了隧道施工期中影响工期的各个因素,并针对隧道工期的风险事件列出事故树,对其进行定性和定量分析,找出影响工期较强的因素,为今后隧道施工风险管理提供依据。
In this paper the important factors influencing the work period of tunnel construction are enumerated and the fault tree is setup. Through the analysis of the fault tree, the major causes of the delay of the tunnel work period are found. The results of the analysis will be very useful for the decision making in the future.