南水北调中线穿黄工程对河势与防洪影响的试验研究 被引量:2

Effect of the Yellow River-Crossing Project in the South-to-North Water Projecton the River Regime and Flood Control
在线阅读 下载PDF
导出
摘要 穿黄倒虹吸工程是南水北调中线的关键性和控制性工程,而工程所在河段又是典型的游荡性河道,河床演变情 况极其复杂,因此研究工程对河道的影响具有重要意义。通过实体模型试验,对工程修建后对所在河段河势与防洪的 影响进行了分析研究,为工程设计提供了科学依据。 The Yellow River-crossing project is the key project and also the control project of Middle Route Project (MRP) for South-to-North transfer. The river reach of the project site is a typical braided river and the fluviomorphological process in river is very complicated. So the study on the effect of the project on the riverbed is significant to the project design. This paper analyses the effect of the project on the river regime and flood control by using of physical model. The results provide scientific basis for project design.
出处 《南水北调与水利科技》 CAS CSCD 2005年第5期9-12,共4页 South-to-North Water Transfers and Water Science & Technology
关键词 南水北调中线 穿黄工程 河势 防洪 实体模型试验 Middle Route Project (MRP) for South to-North transfer Yellow River-crossing project river regime, flood control physical model
  • 相关文献

参考文献6

  • 1[1]水利部南水北调规划设计管理局.南水北调中线穿黄工程专家座谈会会议纪要及南水北调中线穿黄工程方案协调工作大纲[R].水利部南水北调规划设计管理局,2001.
  • 2[2]黄河水利科学研究院.南水北调中线穿黄工程河道模型试验初步报告[R].郑州:黄河水利科学研究院,1996.
  • 3[3]清华大学.南水北调中线工程穿黄河段河床演变规律及对行洪影响的研究[R].北京:清华大学,2002.
  • 4[4]长江科学院.南水北调中线工程穿黄河段动床模型设计及验证试验报告(附专家评审意见)[R].武汉:长江委长江科学院,1996.
  • 5[5]长江科学院.南水北调中线穿黄工程方案泥沙模型试验报告[R].长江科学院,2002.
  • 6[6]长江委长江科学院.穿黄工程与河势防洪研究专题报告[R].武汉:长江委长江科学院,2002.