摘要
阐述采用单元制双直式锅炉的国产125MW汽轮发电机组进行大修后试验时,不点炉利用邻机抽汽实现中压缸冲转至定速,进而完成大修后机组带负荷前的全部试验及试并网。新的试验方案较传统方案可节约燃油160多t,节约生产成本60多万元。
For homemade 125 MW steam turbinegenerator set with double direct firing boilers of a unitized system, the rotationimpulsing of intermediate pressure cylinder and reaching a constant rotation speed had been realized in test after major repair by using extraction steam from neighbouring unit under nonignition condition of the boiler proper, and all tests and trial synchronization for parallel connection with the power network after major repair of the unit being further completed. Compared with traditional scheme, the new test scheme can save fuel oil of more than 160 t, saving production cost of more than 60000 yuan(RMB).
出处
《热力发电》
CAS
北大核心
2005年第9期63-65,共3页
Thermal Power Generation
关键词
125MW机组
邻机抽汽
中压缸冲转
起动
节油
125 MW unit
extraction steam from neighbouring unit
rotationimpulsing of intermediate pressure cylinder
startingup
fueloil saving