V形刚构桥施工中倒三角区域支架的拆除时机分析 被引量:7

Study on the Demolishment Sequence of Scaffolds for the Inverted-triangle Areaof the Rigid-frame Bridges with V-piers
在线阅读 下载PDF
导出
摘要 采用桥梁博士软件模拟一座典型的V形墩连续刚构桥的施工过程,为找出支架拆除对传力途径的影响,分别单独计算结构自重、预应力以及收缩徐变内力,然后对单因素分析的结果进行组合。分析结果表明倒三角区域支架的拆除时机对桥梁在施工阶段及成桥后的内力均有显著影响,可达50%以上。建议优先采用早拆支架方案,以使结构受力明确,且对V形墩区域受力有利。 The paper adopted the software of Bridge Doctor to simulate the construction process of a typical Rigid-frame Bridges with V-piers. The internal force caused by self-weight, prestress, shrink and creep was computed separately to identify the influence of the demolishment sequence of scaffolds on the load transfer. Then, a combination of the factors was discussed. The analysis results indicate that the demolishment sequence of the inverted-triangle area region scaffolds has remarkable influence on the internal force in the construction and completion phase, the difference of which may be greater than 50%. Therefore early demolishment should be preferred so as to make the load transfer more clear and the inverted-triangle area in good condition.
作者 李国亮 刘钊
出处 《公路交通科技》 CAS CSCD 北大核心 2005年第8期95-97,101,共4页 Journal of Highway and Transportation Research and Development
关键词 刚构桥 V形墩 预应力混凝土 支架拆除 Rigid-frame bridge V-shaped pier Prestressed concrete ScaffoM demolishment sequence
  • 相关文献

参考文献2

共引文献19

同被引文献103

引证文献7

二级引证文献15

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部