摘要
本文提出了压力钢管取消伸缩节后厂坝联结结构形式的优选准则,并通过对某大型水电站整体结构进行三维有限元分析,确定了最优模型和最佳明管长度,给出了初步设计阶段明管管壁厚度的计算公式.
An optimum criterion for the structures of junction between dam and power house without expansion joint had been proposed.The structural analysis of a large hydroelectric power station is accomplished by using 3-D finite element method,and an optimal model an optical length of exposed pipe are given with the simple optimization method.Finally,a method to calculate the thickness of exposed pipe is proposed.
出处
《水利学报》
EI
CSCD
北大核心
1995年第8期39-45,共7页
Journal of Hydraulic Engineering
基金
"七五"国家重大技术装备科技攻关项目
关键词
坝后式厂房
水电站
联结
伸缩节
高压管道
hydroelectric power station,penstock,expansion joint,exposed pine, finite element method.