摘要 通过对鹤岗发电厂二期工程扩建项目取水位置、取水量、水质和用水量进行研究,并考虑区域内居民生活、生产的需水及利用水源情况,分析论证本项目开发利用水源的合理性,为本扩建项目水源论证提出公正、科学、合理的结论。 Through the studies of water sourcing location,quantity of getting water water quality and quantity of using water of on extension project of the second stage project of power plant in Hegang,and considering the situation of the residents' demands and water resource, this paper presents the reasonability of developing and utilizing water resource in this project, and draws the justice, scentific, reasonable conclusion of water resource of this project.
机构地区 佳木斯水文局
出处 《黑龙江水专学报》 2005年第1期51-53,共3页 Journal of Heilongjiang Hydraulic Engineering College
关键词 建设项目 取水 水源论证 鹤岗发电厂 constructing project getting water water resource justice Hegang Power Plant
  • 相关文献

参考文献2

  • 1水利部水资源司、水利部水资源管理中心.建设项目水资源论证技术标准汇编[G]. 2003.
  • 2DL/T 5034-94,火力发电厂供水水文地质勘测技术规程[S].

同被引文献15

引证文献2

二级引证文献11

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部