摘要
2003年3月11日500kV神侯二回线316号塔发生故障,结合当地的气候、故障点的位置、故障塔型式、绝缘配置及故障现象,对该次故障进行了综合分析,得出该次故障为冰闪故障的结论,并提出整改建议。
On Mar 11,2003,the fault took place at 316# of 500kV shenhou II transmission line,regarding to the weather at that time,fault position,fault pole type,insulation set and fault appearance,it is entirely analysed to the fault,concluding that ice flashover is the reason of the fault,and improving measurement is submitted.