用控制爆破技术快速开挖水电站岩石地基 被引量:1

USE OF CONTROLLED BLASTING FOR RAPID EXCAVATION OF BASE ROCK IN HYDROPOWER STATION
在线阅读 下载PDF
导出
摘要 凌津滩水电站岩石地基开挖面积和深度大 ,并且受洪水影响 ,开挖工期已经比计划推迟了约 5个月。为加快施工进度 ,采用了“垂直主爆孔、水平主爆孔和预裂孔、孔间微差爆破”等控制爆破技术 ,一次起爆形成设计要求的建基面。文中详细讨论了主爆孔、预裂孔的布孔和装药参数、起爆网路、减震措施 。 In the Lingjintan Hydropower Station,the time limit of rock excavation is delayed by about five months as compared with scheduled time because of large area and depth of excavation and flood impact.In order to quicken rock excavation,the controlled blasting technology is adopted including vertical production holes,horizontal holes of production and presplit,and millisecond delays between holes in a row.By once-through blasting,a qualified foundation surface can be formed with this technology.In this paper,arrangement and charging parameters of production and presplit holes,priming circuit,vibration-reduced measures are discussed in detail and the measures for control of excavation quality are outlined.
出处 《工程爆破》 2004年第4期61-65,共5页 Engineering Blasting
关键词 岩石开挖 深孔爆破 预裂 孔间微差 Rock excavation Deep-hole blasting Presplitting Millisecond delay between holes
  • 相关文献

参考文献2

共引文献20

同被引文献3

  • 1中国力学学会工程爆破专业委员会.爆破工程(上)[M].北京:冶金工业出版社,1996:30-34.
  • 2中国力学学会工程爆破专业委员会.爆破工程(下)[M].北京:冶金工业出版社,1996.
  • 3张志毅,邓志勇.深孔松动爆破关键技术经济指标及效益分析[A].铁道工程爆破文集[C].北京:中国铁道出版社,2000.

引证文献1

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部