摘要
对电厂拟建的4号机的主蒸汽和再热蒸汽参数的组合选型进行了全寿命周期成本(LCC)的理论分析和评估。在机组的招投标选型阶段就从机组的整个运行寿命周期成本考虑,分析了参数变化对机组运行、维护、可靠性、经济性和可用率等影响全寿命周期成本的因素,分析结论可用于机组选型决策。
Analysis and evaluation with life cycle cost theory was performed on the combinations of steam parameters for a newly built No.4 unit of a power plant. The life cycle cost was considered from the very beginning of bidding period. The influence of different combinations of steam parameters on the operation, maintenance, reliability, efficiency and availability of the unit was analyzed and the coming out will be used for decision making.
出处
《华东电力》
北大核心
2004年第11期8-13,共6页
East China Electric Power
关键词
全寿命周期成本评估
机组
额定参数选型
evaluation of life cycle cost
steam parameter combination
type selection