摘要
煤矿采空区的塌陷与变形对高压供电线塔基的稳定构成了极大的威胁.使用高密度电法对塔基附近的地质结构进行了探测,应用二维和准三维反演方法确定了地下电阻率分布形态,以此为基础推断解释了塔基附近煤矿采空区的位置和形态,并对塔基的加固处理提出了建议.
The sinking and deformation occurred in coal mined area do seriously effect the stability and safety on high power tower. High Density Electricity Method is used to survey engineering geology nearby the tower. 2-D and 3-D inversion methods are employed to determine the distribution of the resistivity, and the location and side of the mined cavity can be explained through the underground resistivity distribution. Some proposes are raised to reinforce the foundation of the tower.
出处
《地球物理学进展》
CSCD
2004年第3期684-689,共6页
Progress in Geophysics
基金
中国科学院地质与地球物理研究所工程地质力学重点实验室资助.
关键词
高压线塔基
煤矿采空区
高密度电法
二维和准三维反演
High power tower foundation, coal mined cavity, high density electricity method, 2-D and 3-D inversion.