摘要
以岩巷快速掘进影响因素及其优化措施为对象开展探究。结合具体工程实际,在分析影响岩巷快速掘进因素的基础上,对岩巷快速掘进方案开展了优化探究,并对优化后的方案应用效果进行了探究。结果表明,优化后的方案实现了巷道掘进速度的显著提升,对于保障井下生产的持续开展意义重大。
The influencing factors and optimization measures of rapid excavation in rock roadway was explored. Combining with the actual engineering practice, based on the analysis of the factors affecting the rapid excavation of rock roadway, this paper carried out the optimization exploration of rock roadway rapid excavation scheme and discussed the application effect of the optimized scheme. The results show that the optimized scheme achieves a significant increase in the tunneling speed, which is of great significance for ensuring the continuous development of underground production.
作者
梁超
LIANG Chao(Meiyukou Coal Mine, Datong Coal Mine Group, Datong 037003, Shanxi, China)
出处
《能源与节能》
2019年第6期15-16,36,共3页
Energy and Energy Conservation
关键词
矿井
岩巷掘进
影响因素
优化措施
mine
rock roadway excavation
influencing factors
optimization measures